Crews lose the first half-day of many jobs waiting on access badges, furniture that never moved, and unanswered questions about “what’s in scope.” Use this commercial building prep checklist before painters mobilize in Maryland, D.C., or Northern Virginia.

Key takeaway: If an item is not assigned an owner (tenant, PM, or contractor), assume it will delay day one.
14-day prep (project managers)
- Confirm final scope, colors, and exclusions in writing
- Issue insurance requirements and building rules
- Schedule elevator/loading dock windows
- Notify tenants or residents of work hours and affected areas
- Decide who moves furniture, wall hangings, and storage

- Confirm final scope, colors, and exclusions in writing
- Issue insurance requirements and building rules
- Schedule elevator/loading dock windows
- Notify tenants or residents of work hours and affected areas
Write assumptions into the bid request so crews, property staff, and ownership are evaluating the same job.
7-day prep (facilities / site)
Key takeaway: If an item is not assigned an owner (tenant, PM, or contractor), assume it will delay day one.
- Badge access and parking instructions for the crew
- Identify water sources, restrooms, and staging areas
- Clear corridors and closets that are in scope
- Flag known leaks, stains, or damaged drywall
- Confirm alarm, camera, and after-hours entry procedures
Day-of readiness signals
- Keys/badges work
- Occupied areas have signage and routing
- No surprise “do not paint” surfaces left unmarked
- Other trades are not creating dust in wet-paint zones
Tenant memo bullets you can reuse
Send it early. A good memo prevents half the day-one chaos facilities teams report on paint projects.
- Work dates and daily hours
- Floors/areas affected
- What must be moved off walls and desks near walls
- Expected noise/odor level and ventilation notes
- Contact for access issues the same day
Day-before checklist
- Work zones emptied or ready for protection
- Floor protection path agreed for material transport
- Emergency contacts shared both ways
- Paint storage location temperature-appropriate
- Punch/inspection contact identified for daily questions
Maintenance reality: Clear documentation reduces touch-up confusion and change-order disputes after the crew leaves.
Frequently asked questions
Who should move office furniture?
Decide in the bid. Many commercial jobs include protection but not full furniture moving unless specified.
Do tenants need to empty everything?
Not always—but walls must be accessible. Clear wall hangings and dense storage in work zones.
What if access fails on morning one?
Have a building engineer contact on speed dial. Access failures are the most preventable delay. Need a commercial painting bid in Maryland, D.C., or Northern Virginia?